試卷名稱(chēng) 2017年信息系統(tǒng)項(xiàng)目管理師最新英語(yǔ)模擬題(2)
考試中心《2017年信息系統(tǒng)項(xiàng)目管理師最新英語(yǔ)模擬題(2)》在線考試
試卷年份2017年下半年
試題題型【單選題】
試題內(nèi)容

A client requests a scope change request after accepting the design. This change will have a potential impact on several project components. What is the project manager’s MOST APPROPRIATE response?
A、Convince client to delay change
B、Analysis infects of schedule and cost due to the change, and have meeting with team members
C、If this change is critical, then implement it and inform the CCB
D、Estimate the cost and schedule affected by the change, get approval before implement