活色生香未删版电影完整版,狠狠操综合,投名状在线观看完整版国语未删减下载,国产激情在线,中文字幕天堂在线,换妻换上瘾完整版未删减在线观看 ,谜情家族电视剧粤语在线观看高清

軟題庫(kù) 移動(dòng)APP 掃碼下載APP 隨時(shí)隨地移動(dòng)學(xué)習(xí) 培訓(xùn)課程
試卷名稱 信息系統(tǒng)項(xiàng)目管理師-pmp練習(xí)題-2
考試中心《信息系統(tǒng)項(xiàng)目管理師-pmp練習(xí)題-2》在線考試
試卷年份2017年下半年
試題題型【單選題】
試題內(nèi)容

A manufacturing project is conducted under limited time constraints. At the point of delivery, a large batch of components must be scrapped, as they do not meet the industry minimum requirements. What should the project manager have done to prevent this problem?
A、Surveyed the industry standards and enterprise environmental factors.
B、 Initiated quality audits to ensure that the planned quality assurance activities are followed.
C、 Increased the focus on risk identification, mitigate and contingencies.
D、 Obtained approval from the sponsor to extend project time line.


相關(guān)試題

推薦文章